Project process

How a modular cabin order works.

Keep product selection, order information and local site responsibilities connected from the first review onward.

Finished unit walkthrough · real footage

Five connected stages

Move forward with the right input.

No two projects share a timeline. These stages exist so scope and handoffs are settled in order — not discovered on site.

  1. 01

    Share the brief

    Start with use, destination, quantity, site access, utilities and target timing.

    You provide
    Project context and known constraints
    Review result
    The questions and product families worth reviewing
  2. 02

    Compare systems

    Choose the building form before narrowing models, finishes and room layouts.

    You provide
    Priorities, occupancy and preferred layouts
    Review result
    A focused family and model recommendation
  3. 03

    Review the scope

    Separate the product package from approvals, foundations, lifting and local works.

    You provide
    Site conditions and local-team inputs
    Review result
    Open items, interfaces and responsibilities
  4. 04

    Confirm the order

    Use the quotation, drawings and configuration list as the shared order record.

    You provide
    Approved selections and agreed information
    Review result
    Confirmed product and order information
  5. 05

    Prepare delivery

    Coordinate receiving, access, lifting, temporary storage, foundations and utilities.

    You provide
    Local receiving and installation plan
    Review result
    A defined handoff before dispatch
  6. 06

    Install on site

    The local team follows the staged method statement, with hold points and inspection records at every stage.

    You provide
    Installation crew, crane and site supervision
    Review result
    The method statement, readiness checks and stage records
  7. 07

    Hand over

    Close-out checks, punchlist and the delivered document set complete the project record.

    You provide
    Final walkthrough and acceptance
    Review result
    Drawings, test records and operating information

Responsibility clarity

Confirm the package and site scope.

AeroPodHomes review

Product-family comparison, available options, configuration inputs, drawings and order information.

You confirm

Destination, quantity, use, room priorities, approved selections and the target delivery period.

Local teams complete

Approvals, civil work, foundations, lifting, final utility connections and site completion.

Modular building placement and receiving work at a project site
Placement reference · local access and lifting plan required

Before dispatch

Prepare the receiving plan.

  • Access route and lifting position
  • Foundations or support points
  • Temporary storage and protection
  • Final utility and installation responsibilities

Before you sign

Twenty checks that belong in every modular contract.

Scope, engineering evidence, transport, site responsibilities and handover — the list our project documents are built to answer. Take it into any quotation conversation, including ours.

Next step

Start with your site brief.

Share location, use, quantity, access and timing.

Request review